St Paul's Church, Penketh. Rebuilding in progress....

This is my photo record of the rebuild project.
I am hoping to visit regularly to take photos of progress.
Click on any photo to expand it, or if video is available
display the video. Videos require the use of an up-to-date browser,
if you get a blank screen or error message, try a different browser.


Links to earlier (and later) pages, now by dates:

Friday, 24th March, 2017

Several items this week. The cladding on the front of the admin block is finished - photos taken on 21st but didn't get a chance to upload them until today.

Trench along front and west side of building for water and gas. Water pipe being laid. Also space for pedestrian entrance excavated up to the boundary wall.

The first glazing panels installed today at front of the building.

Additions to the plant room. Internal brickwork all finished.


Cladding on front of the office.

Trench along front for water and gas.

Trench along side with water pipe.

Excavation for pedestrian entrance.

First glass panels in place.

Fitting another panel.

Front windows from inside.

Electricity switch box, no breakers yet.

Twin pumps for heating system.

Toilet wall finished.

Kitchen wall finished

Rainwater drainpipe in ladies loo.


The building fund is currently well below the amount needed to complete the building. The money we currently have will only suffice to complete the shell of the building.
In order to fit out the interior we need a lot more money. If you would like to make a donation towards this, then please click this link. Thank you!

We have recently received a couple of anonymous donations which are much appreciated. If either was from you, then we are deeply grateful. Thank you very much!