Thursday, 6th April, 2017
Only one week left to handover!
The work on drains and front entrance ramps and steps continues. Screeding over the heating pipes has started and already covers a goodly part of the admin block, as well as the creche area. By the end of today I would expect that to be completed.
Timber cladding for the rear wall has arrived and should be in place by the end of this week. Hardcore laid for part of the path between the front entrance and the car park. Still a fair number of glass panels to be installed, to say nothing of the doors! Further assurances that all will be ready by the 13th, excluding the car park.