Friday, 28th April, 2017
[ Apologies for the late appearance of this page - I now realise that I had forgotton to upload the page to the website, and a couple of later pages have gone up in the meantime. This page has now been inserted in the correct date order. ]
Lots of progress in the last couple of days. The roof lights have been installed over the lobby area.
The capping which seals the top of the walls has arrived and installed over the main hall. Work now progressing on the lower roof.
Paving is almost complete; doors and windows are being tidied up, cleaned and checked.
Tidying up of the car park area progresses, with another cabin gone, and the site office relocated