The building is now almost complete, minor adjustments to windows and doors still in progress, but interior now very tidy. Main work now is the car park. The outline has now been set out with kerbstones, and further paving along the East side of the main hall is expected any day now.
The front pedestrian entrance has been completed with the addition of capstones on the pillars.
The Bin store area has been fitted with wooden screens.
Handover could possibly be next week!