Links to earlier (and later) pages, now by dates:




Tuesday, 7th March, 2017
The main hall roof is finished (sorry no photo yet), and the scaffolding should have come down but hasn't. The roof over the admin area is still to do, but that shouldn't hold up other work.
Internally, the electricity supply has been connected up to a board and meter, so there is mains available - 2 double 13-amp sockets!
No water supply as yet, though the water meter has been installed in the plant room.
The heating boilers and associated pipework have been installed and await connection to the gas main and water. Further plumbing work due later this week.