Friday, 24th March, 2017
Several items this week. The cladding on the front of the admin block is finished - photos taken on 21st but didn't get a chance to upload them until today.
Trench along front and west side of building for water and gas. Water pipe being laid. Also space for pedestrian entrance excavated up to the boundary wall.
The first glazing panels installed today at front of the building.
Additions to the plant room. Internal brickwork all finished.