St Paul's Church, Penketh. Rebuilding in progress....

This is my photo record of the rebuild project.
I am hoping to visit regularly to take photos of progress.
Click on any photo to expand it, or if video is available
display the video. Videos require the use of an up-to-date browser,
if you get a blank screen or error message, try a different browser.


Links to earlier (and later) pages, now by dates:

Friday, 24th March, 2017

Several items this week. The cladding on the front of the admin block is finished - photos taken on 21st but didn't get a chance to upload them until today.

Trench along front and west side of building for water and gas. Water pipe being laid. Also space for pedestrian entrance excavated up to the boundary wall.

The first glazing panels installed today at front of the building.

Additions to the plant room. Internal brickwork all finished.


Cladding on front of the office.

Trench along front for water and gas.

Trench along side with water pipe.

Excavation for pedestrian entrance.

First glass panels in place.

Fitting another panel.

Front windows from inside.

Electricity switch box, no breakers yet.

Twin pumps for heating system.

Toilet wall finished.

Kitchen wall finished

Rainwater drainpipe in ladies loo.


The building fund is growing, but slowly. We have received promised grants, but still need quite a bit more to fund completion. We have do have enough money to make a start on the fitting out process, but it will only cover part of the job. The sooner we have the money the sooner we will be able to complete the building and start making use of it.

If you would like to make a donation towards this, then please click this link. Thank you!

We have recently received a number of donations which are much appreciated. If one was from you, then we are deeply grateful. Thank you very much!